Duration of project: The project was completed within 4 months
Brief description of the project: The house suffered a fire due to a direct lightning strike. This resulted in significant damage to the property due to smoke and water damage.
Duration of project: The project was completed within 5 months
Brief description of the project: The owner of the home was older and suffering from mobility issues. We were tasked with completing a series of adaptions to their home and garden to improve access to their home.
Brief description of the project: The house suffered a fire that caused significant damage to the property from smoke and water. We stripped back the damaged areas before completing the restoration. Which included the replacement of a structural section of the roof, new windows and doors, cleaning and thermal fogging to smoke-damaged rooms, new bathrooms, and carpentry, including bespoke fitted wardrobes, flooring and decoration throughout.
Brief description of the project: We were tasked with completing roof works to property in Woking which had been leaking into the Sainsburys store situated below. We completed a series of works to the flat roof, which included some localised repairs, resetting of the stone parapet wall caps and the preparation and installation of a Sika Liquid Plastics Decothane Ultra Top-Up 10 / Sikalastic Rapid Coating System with an added Sikalastic Rapid Trafficable Waterproofing and Wearing System. A complex project which required us to liaise with the business below, and also communicate with the six tenanted properties, who required access to the roof area to access to their front doors. The Sika product installed offers a 15-year Workmanship and Manufacturer’s Guarantee and peace of mind to our client.
Maida Vale
Name of project: Structural repairs, Maida Vale
Name of client: Accord Surveying
Value: £55,000
Project duration: 3 months
Brief description of the project: Due to historic bomb damage, we were instructed to complete stabilisation works on an external wall, which used to be the party wall for an existing property that was destroyed.
Brief description of the project: Following a survey of these HMO properties, it was found that the internal doors were not compliant with current fire regulations. The project was to install new fire doors to all habitable rooms, kitchens and garages. This included making good and local decorations.
Bordon
Name of project: Commercial project, Bordon
Name of client: Accord Surveying
Value: £135,000
Project duration: 4 months
Brief description of the project: Following a tenancy renewal and full survey of the building. It was found that the means of escape, fire doors and general layout of the property were lacking. We were awarded a tender to install a full fire alarm system, means of escape corridors and new fire doors throughout the property after achieving full compliance certification from building control.
The Brambridge Shop
Name of project: Dilapidation survey, Brambridge
Name of client: Private client
Value: £20,000 + fees
Project duration: 4 weeks
Brief description of the project: We were employed to complete a full dilapidation survey following the end of a tenancy. The property required a number of remedial works to bring it back to its pre-let condition, and we were able to secure the landlord a settlement of circa £20,000 to complete the necessary repair works.